June 2009 |
Project launch |
October 2010 |
Task 1 working document published. |
December 2010 |
Questionnaires related to Task 2&3 sent to stakeholders |
|
|
March 2011 |
Tasks 2-3 working documents published |
April 2011 |
The first stakeholder meeting was held on Monday 18th April |
August 2011 |
Task 4 working document to be published |
September 2011 |
Task 5 working document to be published |
September 2011 |
Task 6 working document to be published |
End of September 2011 |
Second stakeholder meeting will be held on Wednesday, 28th September 2011 |
February 2012 |
Tasks 7 and 8 working documents to be published |
March 2012 |
Third stakeholder meeting to be held |
April 2012 |
Final report to be published |